PMP Certification Executing Questions Test 5

© examsiri.com
Question : 30 of 70
 
Marks: +1, -0
A software business partner of a project is delayed in the delivery of the requirements. The business partner is working remotely as a virtual team and the contract includes penalties if the dates are not met. At this point, the application of the penalties impacts the budget's baseline.
What should the project manager have done to avoid this situation?