A project is in its execution phase and many change requests are being implemented. One change request activated new equipment to replace obsolete equipment. Although no longer in use, the obsolete equipment was not disposed of or switched off properly, generating maintenance costs and energy consumption that serve no purpose.
What did the change executor fail to observe?