Question : 28 of 70
Marks:
+1,
-0
A project manager is assigned to a project in its execution phase. The project manager immediately notices scope creep, but the development manager justifies the additional work and claims it is in line with a new policy approved by management.
What should the project manager do to address this situation?
What should the project manager do to address this situation?