TS ICET 2015 Question Paper with Solutions for online practice

© examsiri.com
Question : 109 of 200
 
Marks: +1, -0
10 men and 15 women can complete a work in 6 days; and 12 men and 27 women can complete the same work in 4 days. The number of days required for 2 men and 12 women to complete the same work is