SSC CHSL 12 Oct 2020 Shift 3 Paper

© examsiri.com
Question : 66 of 100
 
Marks: +1, -0
Shyam can complete a task in 12 days by working 10h a day. How many hours a day should he work to complete the task in 8 days?
Go to Question: