RRB NTPC Mains or Stage 2 Model Paper 7 with solutions
© examsiri.com
Question : 32 of 120
Marks:
+1,
-0
C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?