Question : 32 of 70
Marks:
+1,
-0
A project manager working with a risk-averse financial firm has just started a new project. The project sponsor is extremely concerned that the project may run over budget and is looking to the project manager for confirmation that this won't happen.
In order to alleviate the sponsor's concern, what should the project manager do?
In order to alleviate the sponsor's concern, what should the project manager do?