PMP Certification Planning Questions Test 3

© examsiri.com
Question : 31 of 70
 
Marks: +1, -0
The estimated cost of completing all the activities considered in a schedule will be US$14,500. The project's sponsor requires a level of certainty about the cost baseline of at least 90%. As a result of a Monte Carlo simulation, the projected cost calculated is:
ProbabilityEstimated Cost
40%US $ 10,000
50%US $ 12,000
60%US $ 13,000
70%US $ 15,000
80%US $ 18,000
90%US $ 20,000
100%US $ 21,000
What should the contingency reserve be in order to fulfill the sponsor's requirement?
Go to Question: