PMP Certification Planning Questions Test 3
© examsiri.com
Question : 31 of 70
Marks:
+1,
-0
The estimated cost of completing all the activities considered in a schedule will be US14,500. The project's sponsor requires a level of certainty about the cost baseline of at least 90%. As a result of a Monte Carlo simulation, the projected cost calculated is:
What should the contingency reserve be in order to fulfill the sponsor's requirement?
| Probability | Estimated Cost |
| 40% | US 10,000 |
| 50% | US 12,000 |
| 60% | US 13,000 |
| 70% | US 15,000 |
| 80% | US 18,000 |
| 90% | US 20,000 |
| 100% | US 21,000 |
Go to Question: