Question : 22 of 71
 
Marks: +1, -0
In a long-running project, both approved and rejected changes have been managed successfully via the change control process. But lately, the change control board (CCB) has been slow to process change requests. Therefore, due to time constraints, some changes are being evaluated by team members instead of following the process, and this trend is increasing.
What should be done to avoid scope creep?