PMP Certification Monitoring and Controlling Test 4

© examsiri.com
Question : 21 of 71
 
Marks: +1, -0
During a review meeting, the project manager realizes that scheduled quality control inspections were not conducted. Since the project is running short on time, the project manager decides to hold a joint customer acceptance inspection.
What should the project manager do next?