PMP Certification Monitoring and Controlling Test 1
© examsiri.com
Question : 60 of 70
Marks:
+1,
-0
While controlling project work, the team discovers that the schedule performance index (SPI) is 0.8 and the cost performance index (CPI) is 0.95. If the schedule for this project is a priority and no additional resources are available, what should the project manager do?