A construction organization's change management policy states that changes not regarding project baselines can be revised and approved by functional managers, but changes regarding baselines must be revised by the change control board (CCB). The CCB meets once a month. A project manager in charge of a water supply project must obtain authorization to use a contingency reserve and continue with the project, but the next CCB meeting is in two weeks.
What should the project manager do?
What should the project manager do?