PMP Certification Executing Questions Test 6

© examsiri.com
Question : 24 of 41
 
Marks: +1, -0
After performing a risk analysis, the project manager realizes that the project team may be unable to develop a final project module on time and within quality standards. This could cause a financial loss to the company. The project manager decides to engage a vendor to deliver that module using a firm fixed price (FFP) contract.
What risk response strategy did the project manager use?
Go to Question: