PMP Certification Executing Questions Test 6
© examsiri.com
Question : 23 of 41
Marks:
+1,
-0
A project's budget at completion (BAC) is US100,000, its earned value (EV) is US20,000, and its actual cost (AC) is US10,000. The planned value (PV) is US20,000.
What efficiency must be maintained to achieve the current estimate at completion (EAC)?
What efficiency must be maintained to achieve the current estimate at completion (EAC)?