Question : 24 of 70
 
Marks: +1, -0
Since the client was on leave, a project manager handed over the deliverables of a successfully completed project to the client's project manager. One month later, the accounts team informs the project manager that client approval was rejected and invoices are unpaid.
What should the project manager have done to avoid this?