PMP Certification Executing Questions Test 4

© examsiri.com
Question : 23 of 70
 
Marks: +1, -0
A new project manager is taking over a project being done for a company in another country. The project manager learns that the project has a fixed price and that the project is being paid for in the local currency, which has been fluctuating. The project sponsor thinks this is too risky and wants the project manager to address it at the next risk review board.
What should the project manager recommend at the risk review board?
Go to Question: