PMP Certification Executing Questions Test 1

© examsiri.com
Question : 41 of 70
 
Marks: +1, -0
While preparing a project's third progress report, the project manager identifies that the project will experience delays due to late material deliveries. The two previous project reports indicated that the project was on track. What should the project manager do next?