PMP Certification Executing Questions Test 1

© examsiri.com
Question : 40 of 70
 
Marks: +1, -0
The project manager of a pipeline project hires a construction contractor using a cost plus fixed fee (CPFF) contract. The contractor provides the project manager with an estimate of US$50,000, and a fixed-fee amount of US$5,000. When the pipeline is completed, the construction cost is US$60,000. What amount should the contractor be paid?
Go to Question: