A project requires five tasks to complete.
Task A begins on day 1 and will take two days to complete.
Task B will take six days to complete and cannot begin until task A is finished.
Task C will take four days to complete, cannot begin before task A is finished, and must be completed before task D begins.
Task D will take eight days to complete and cannot begin until task B is finished. Task E will take one day to complete and cannot begin until task D is finished.
What is the duration of the critical path?
Task A begins on day 1 and will take two days to complete.
Task B will take six days to complete and cannot begin until task A is finished.
Task C will take four days to complete, cannot begin before task A is finished, and must be completed before task D begins.
Task D will take eight days to complete and cannot begin until task B is finished. Task E will take one day to complete and cannot begin until task D is finished.
What is the duration of the critical path?