A project just completed acceptance testing, and two percent of identified issues are still pending. Even though these are non-critical issues, some stakeholders are reluctant to accept the deliverables. Therefore, the project cannot proceed to the next phase.
What should the project manager have done to avoid this?
What should the project manager have done to avoid this?