Management Aptitude Test 2016 Paper

© examsiri.com
Question : 91 of 200
 
Marks: +1, -0
A alone would take 27 days more to complete the job than both A and B would together. If B worked alone, he took 3 days more to complete the job than A and B worked together. What time would they take, if both A and B worked together?
Go to Question: