Question : 82 of 190
Marks:
+1,
-0
Quantity A : P and Q together Q and R together and Rand P together can complete a piece of work in 12, 15 and 24 days respectively. In how many days can Q finish the work alone?
Quantity B : S & T working alone can complete a work in 10 and 15 days respectively. They started together but after 5 days S left, in how many days will be total work be completed?
Quantity B : S & T working alone can complete a work in 10 and 15 days respectively. They started together but after 5 days S left, in how many days will be total work be completed?