GATE Mechanical Engineering (ME) 2022 Shift 2 Solved Paper

© examsiri.com
Question : 42 of 65
 
Marks: +1, -0
A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is ______ weeks (in integer).
Activity
Time estimates (in weeks)
Immediate predecessor(s)
Optimistic time
Most likely time
Pessimistic time
A
4
5
6
None
B
1
3
5
A
C
1
2
3
A
D
2
4
6
C
E
3
4
5
B, D
  • Your Answer:
Go to Question: