Question : 41 of 65
Marks:
+1,
-0
Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.
|
Part |
Milling (hours) |
Polishing (hours) |
|
P1 |
8 |
6 |
|
P2 |
3 |
2 |
|
P3 |
3 |
4 |
|
P4 |
4 |
6 |
|
P5 |
5 |
7 |
|
P6 |
6 |
4 |
|
P7 |
2 |
1 |