GATE Mechanical Engineering (ME) 2019 Shift 2 Solved Paper

© examsiri.com
Question : 39 of 65
 
Marks: +1, -0
The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “X < Y, Z” means that X is predecessor of activities Y and Z. The time to complete the activities along the critical path is ____________ weeks.
ActivityDuration
(Weeks)
Precedence
Relationship
A5A < B, C, D
B7B < E, F, G
C10C < I
D6D < G
E3E < H
F9F < I
G7G < I
H4H < I
I2---