Question : 38 of 65
 
Marks: +1, -0
The figure shows a pouring arrangement for casting of a metal block. Frictional losses are negligible. The acceleration due to gravity is 9.81m/s2. The time (in s, round off to two decimal places) to fill up the mold cavity (of size 40cm×30cm×15cm ) is