The uniform arrival and uniform service rates observed on an approach road to a signalized intersection are 20 and 50 vehicles/minutes, respectively. For this signal, the red time is 30s, the effective green time is 30s, and the cycle length is 60s. Assuming that initially there are no vehicles in the queue, the average delay per vehicle using the approach road during a cycle length (in s, round off to 2 decimal places) is ___________