UPSC CDS 2 2021 Math Paper
© examsiri.com
Question : 21 of 100
Marks:
+1,
-0
20 men are supposed to complete a work in 10 days after working for 5 days they realise that only one fourth of the work is done. How many more men they need to employ to finish the work on time?