UPSC CDS 2 2018 Math Paper
© examsiri.com
Question : 44 of 100
Marks:
+1,
-0
X and Y together can finish a job in 6 days. X can alone do the same job in 12 days. How long will Y alone take to do the same job ?
[2018 CDS-II]