UPSC 2014 CDS II Math Paper
© examsiri.com
Question : 3 of 100
Marks:
+1,
-0
A, B and C can do a piece of work individually in 8, 12 and 15 days respectively. A and B start working together but A quits after working for 2 days. After this, C joins and works till completion of the work. In how many days will the work be completed?
[2014 CDS-II]