UPSC 2014 CDS I Math Paper

© examsiri.com
Question : 11 of 100
 
Marks: +1, -0
15 men complete a work in 16 days. If 24 men are employed, then the time required to complete that work will be
[2014 CDS-I]
Go to Question: