Question : 8 of 40
Marks:
+1,
-0
Rohan and Sohan undertook to do a piece of work for Rs 7,200 that Rohan alone can do in 4 days and Sohan in 6 days but with the help of Shruti, they finished it in just 2 days. Shruti’s share will be: