Time and Work Practice Test 2 with solutions

© examsiri.com
Question : 25 of 40
 
Marks: +1, -0
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days, with the help of C they did the job in 4 days only. Then C alone can do the job in: