SSE JE Electrical Engineering 28 Oct 2020 Shift 1 Papers

© examsiri.com
Question : 182 of 200
 
Marks: +1, -0
For a power plant maximum demand is 50 MW and the sum of individual maximum demands is 56 MW. Find the diversity factor.
Go to Question: