SSC Steno Grade C and D 7 Aug 2025 Shift 1 Paper

Section: General Intelligence & Reasoning
© examsiri.com
Question : 20 of 200
 
Marks: +1, -0
If 4 workers can complete a job in 12 days, how many days will 6 workers take to complete the same job? 
Go to Question: