SSC JE Civil Engineering 30-Oct-2020 Shift 1 Paper
© examsiri.com
Question : 105 of 200
Marks:
+1,
-0
Calculate the approximate number of cement bags required for preparing wet concrete of 10 m by volume in 1 ∶ 3 ∶ 6 mix proportion. Consider dry volume of concrete to be 1.54 m per cubic metre of wet concrete.