An airport runway fill needs 8,50,000 of soil compacted to a void ratio of 0.7. The required soil is to be taken from a borrow pit having an in situ void ratio of 0.8. If the transportation cost is Rs.10 per , the estimated cost for the filling work is (in Rs.):
Concept: While excavating the soil from the borrow pit and after that compacting it, the mass of solids and its specific gravity will not change, and hence, the volume of solids remains constant even after compaction. The Total volume(V) of soil is given by
Where Total volume of soil, Volume of voids, Volume of solids Divide the equation (i) by (Volume of solids)
Calculation: Condition - I: Filling and So, Volume of solids in filling
Condition-I: Excavation The volume of solids will be the same as that of during fill i.e.
So, find the volume of excavated soil
The estimated cost for the filling work is (in Rs.) = 10 × 900000 = 90,00,000