Directions (Q. 142–146): The table given below shows the estimated cost of various items (in lakhs) in a construction project of a real estate company from 2009 to 2012. Study the table and select the most appropriate answers.
| Year&Item | 2009 | 2010 | 2011 | 2012 |
|---|---|---|---|---|
| Cement | 84 | 96 | 95 | 105 |
| Steel | 65 | 70 | 72 | 84 |
| Brick | 126 | 140 | 150 | 154 |
| Tiles | 32 | 27 | 36 | 40 |
| Hardware | 56 | 60 | 69 | 65 |
| Electrical items | 12 | 14 | 12 | 20 |
| Other materials | 25 | 31 | 34 | 33 |
© examsiri.com
Question : 145 of 200
Marks:
+1,
-0
If the actual cost exceeds the estimated cost of the company, then the additional cost is cut down by decreasing the cost of bricks. By what percentage of cost on bricks was reduced in 2011, if the actual cost of the company in that year was ` 486 lakhs?