SSC CPO 12 Mar 2019 Shift 1 Paper
© examsiri.com
Question : 115 of 200
Marks:
+1,
-0
The efficiencies of A, B and C are in the ratio 4 ∶ 5 ∶ 6. Working together, they can complete a work in 12 days. In how many days will A alone be able to complete that work?