Question : 15 of 100
Marks:
+1,
-0
Sumit and Amit undertook a work for Rs 7200. Sumit alone can do the work in 5 days and Amit alone can do the work in 4 days. If they work together, then what will be the difference (in Rs.) in the amount they receive?