SSC CGL Tier II 25 Oct 2015 Paper 1

© examsiri.com
Question : 33 of 100
 
Marks: +1, -0
P and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is
Go to Question: