SSC CGL Tier II 25 Oct 2015 Paper 1

© examsiri.com
Question : 24 of 100
 
Marks: +1, -0
A and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A, B, C complete it in 6 days. Number of days required to finish the work by A and C is