SSC CGL Tier II 21 Sep 2014 Paper
© examsiri.com
Question : 59 of 100
Marks:
+1,
-0
A, B and C can do a job in 6 days, 12 days and 15 days respectively. After of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the work is
Go to Question: