Question : 41 of 50
Marks:
+1,
-0
A Belt gathered the following defect data for a polyurethane production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:
Data:
Data:
| Trimming | 37 |
| Forming | 61 |
| Packaging | 29 |
| Sealing | 5 |