Six Sigma Lean Yellow Belt Certification Questions Part 1

© examsiri.com
Question : 41 of 50
 
Marks: +1, -0
A Belt gathered the following defect data for a polyurethane production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:
Data:
 Trimming  37
 Forming  61
 Packaging  29
 Sealing  5