Question : 9 of 35
Marks:
+1,
-0
A Belt gathered the following defect data for a shoe production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:
Data:
Cutting 38
Forming 17
Stitching 56
Sealing 42
Data:
Cutting 38
Forming 17
Stitching 56
Sealing 42