Scrum Product Owner Certification Practice Test 2
© examsiri.com
Question : 33 of 50
Marks:
+1,
-0
Only the Product Owner has the authority to cancel a Sprint. However, the Development Team is trying to convince the Product Owner that the Sprint should be cancelled. What's the right response from the Scrum Master?