Peter is a new Product
Owner on a newly formed Scrum Team. Peter has projected a product completion date based on an
estimated velocity of 21 completed points per Sprint. After the first 3 Sprints, the team has
determined that their maximum velocity is 15 points and they are unable to create shippable
increments at the end of each Sprint. What is the best way to proceed?