SBI PO Prelims 17 Dec 2022 Shift 1 Paper
© examsiri.com
Question : 41 of 100
Marks:
+1,
-0
A can complete a work in 60 days. B is 25% more efficient than A. They work together for 15 days. C alone completes the remaining work in 14 days. B and C together will complete
th part of the original work in:
Go to Question: