SBI PO Prelims 1 Nov 2023 Paper

Section: Quantitative Aptitude
© examsiri.com
Question : 33 of 100
 
Marks: +1, -0
P, Q, and R collectively are able to complete a task in 16(4/11) days, while P and Q together can finish the same task in 20 days. Considering these rates, can you determine how many days it would take for R alone to complete 60% of the task?