Question : 37 of 100
 
Marks: +1, -0
A and B can complete a piece of work in 80 days and 120 days respectively. They started working together but A left after 20 days. After another 12 days C joined B and they completed the remaining work in 28 more days. In how many days can C alone complete the work?